Our products go through rigorous testing before reaching our customers. The video above shows the three-point bend test that our products are subjected to on a daily basis.

We test our products to the ASTM D8364 – the international specification standard for GCCMs.

Concrete Canvas is the first GCCM in the world to meet this standard.

A three-point bend test, also known as a flexural test, is a mechanical test used to determine the flexural strength and stiffness of a material. This test involves applying a load to the centre of a specimen supported at two points, causing it to bend. The key objective is to measure the material’s response to bending forces, which includes the maximum stress and strain it can withstand before failure. This test is performed to the ASTM D8058 standard, an indicator of overall performance.

Further information about our testing procedures are available here:

Technical Note I

Technical Note II

Technical Note III

In July 2023, Concrete Canvas Ltd’s revolutionary product, CCX-MAT® GCCM (CCX-M®), was employed to address a critical need in a hydroelectric project in Semarang, Java, Indonesia. The product was used to line and provide erosion control for a water diversion channel, demonstrating the potential for innovative materials in enhancing the sustainability and efficiency of hydroelectric projects.

CCX-M River Diversion Indonesia

Click here to watch the case study video

The Challenge

The water diversion channel was designed as a temporary structure with the goal of blocking and diverting water run-off from the hydroelectric project site. The channel was intended to be fully submerged within two years, making it essential to line the channel to prevent erosion and water seepage into the surrounding area.

Traditional Solutions Fall Short

Initially, traditional poured concrete was suggested for lining the channel. However, the remote location and scale of the project made this approach financially unfeasible due to high costs associated with logistics, materials, specialist equipment, and labour. Similarly, shotcrete was considered and initially used, but it failed to adhere to the existing soil, further complicating the project.

The CCX-M® Solution

CCX Indonesia

CCX-M® emerged as the optimal solution for this hydroelectric project. This Type II GCCM, as defined in ASTM D8364 – Standard Specification for GCCMs, is ideal for lining hydraulic structures with both soil and solid subgrades. The choice of CCX-M® was driven by its ease and speed of transportation and installation, which required minimal equipment and a small team, significantly reducing overall costs.

Preparation and Installation

Before the installation of CCX-M®, the 360-meter-long channel was excavated and prepared to precise specifications. Anchor trenches were excavated at the shoulders, upstream, and downstream of the channel. Bulk Rolls of CCX-M® were transported to the site and lifted into place using a crane with a spreader beam attachment. The material was laid transversely across the channel’s width and cut to length with basic hand tools. The installation process involved overlapping each layer of CCX-M®, secured with stainless steel screws along the overlap marker line. The material was hydrated after each shift using a hose and water pumped from a nearby stream.

CCX Indonesia

Project Success

Thanks to the speed and ease of application, the CCX-M® was installed at an impressive rate of 700m² per day (during 7-hour shifts) by a team of nine installers. The project was completed ahead of schedule, earning praise from both the clients, The Ministry of Public Works & Housing Indonesia, and the sub-contractors, PT Prima Minechem Indonesia.

ConclusionAerial View CCX Indonesia River Diversion

The successful use of CCX-MAT® GCCM in this hydroelectric project highlights the importance of innovative materials in the construction and maintenance of hydraulic structures. The project in Semarang serves as a model for future hydroelectric projects, demonstrating how advanced materials can provide effective solutions for erosion control, cost efficiency, and project sustainability.

 

View the full case study here.

Our New Product Introduction Manager, Simon Lester has been featured in this month’s Irrigation Leader magazine, you can read the article, below!

Simon Lester Irrigation Leader Cover

Concrete Canvas has a new solution to eliminate seepage loss: a flexible, concrete-filled fabric that hardens on hydration to form a thin, durable, waterproof, and lower-carbon concrete layer. In this interview, Simon Lester, Concrete Canvas’s new product introduction manager, introduces CCX, the company’s next-generation roll-it, lay-it, and spray-it solution that allows customers to line their own canal or ditch in a day.

Simon CCX

Irrigation Leader: Please tell us about your background and how you came to be in your current position.

Simon Lester: I was born in Cape Town, South Africa, where my father worked as an accountant for 50 years. Having attended school and university in South Africa, I got my undergraduate in psychology and geography. I then spent a couple of years traveling overseas, teaching English in Taiwan and backpacking through Southeast Asia. While backpacking, I decided to go back to university to get a civil engineering degree. After graduating in 2005, I went into construction, working predominantly on concrete structures for highways in Swaziland. In 2010, I was looking for an alternative for a canal lining project we were bidding on in Swaziland when I came across an advertisement for Concrete Canvas. I flew to the UK and met William Crawford and Peter Brewin, the inventors and owners of Concrete Canvas. I immediately fell in love with the product and became a distributor for Malawi, Mozambique, Swaziland, and Zambia.

At this stage, I was focusing predominantly on using Concrete Canvas for the lining of irrigation canals on sugar estates. These estates had a mixture of unlined and geomembrane- or concrete-lined canals. Working with these clients on a number of initial projects provided me with the opportunity to understand the requirements and challenges irrigators face on a day-to-day basis. In those days, Concrete Canvas was a new technology in Africa as well as globally, so competing with traditional lining techniques in the irrigation sector was tough. It didn’t work out at that stage, but I stayed affiliated with Concrete Canvas, and in 2015, Mr.Crawford and Mr.Brewin offered me a job as the business development manager for subSaharan Africa. I started that role in 2016 and have been with the company ever since. In 2020, I took on my current role as new product introduction manager for CCX, our next-generation product, and I emigrated to the UK with my wife and three sons to take up a position at our head office just outside Cardiff in Wales.

Simon CC Sales Partner Meet

Irrigation Leader: Please introduce Concrete Canvas.

Simon Lester: Concrete Canvas was developed out of a master’s thesis by William Crawford and Peter Brewin. They were looking for a cementitious product that essentially mimicked the performance of a plaster of Paris bandage. Initially, Concrete Canvas was used to create rapidly deployable inflatable shelters that could be used in war-torn or disaster-stricken areas. The shelters were designed to be inflated and then sprayed with a Concrete Canvas surface that cured in position. Within 24 hours, they were habitable. Mr. Crawford and Mr. Brewin quickly realized, though, that the shelter skin had much greater potential in erosion-control applications such as lining ditches and protecting slopes. In 2009, Concrete Canvas became commercially available on an industrial scale. It was initially manufactured in Pontypridd, in South Wales, but as demand has grown, we’ve had to increase production capacity, resulting in a move to our current premises in Pontyclun. Today, nearly 90 percent of our products are exported around the world to some 80 countries. Our core applications are ditch and canal lining, slope protection, the remediation of existing concrete infrastructure, weed suppression, and secondary containment applications.

CCX Installation in the US

Irrigation Leader: How long have you been operating in the United States?

Simon Lester: Our U.S. company officially opened in Houston in 2021. We used to operate on a purely distribution basis, with several distributors across the country covering different territories and sectors. Melanie Fuhrman is the general manager of Concrete Canvas USA and heads up a great in-country team covering sales, technical matters, and logistics.

Simon at the CCUSA Partner Meet

Irrigation Leader: Please tell us about your CCX products.

Simon Lester: Concrete Canvas is a flexible, concrete-filled fabric that hardens on hydration to form a durable, waterproof concrete layer. The concrete hard-armoring provides the strength and protection functionality, while the geomembrane backing provides the waterproofing functionality. The product that we predominantly use for lining canals in irrigation applications is called CCX. In one application, it provides what would typically require multiple products or component applications in the field. This is fundamental to a lot of our clients, especially in the irrigation sector, because they have limited time during the off-season to implement a lining solution or remediate existing canals. The product comes in a prefabricated roll. You pull it off the roll, lay it, cut it with a utility knife or rotary cutter, fix it place, and spray it with water. Within a day, you have a usable lining solution. It’s quick and simple to install, and it doesn’t require skilled labor, allowing most irrigators the option to do it themselves. CCX has a minimum lifespan of 50 years and is cost competitive with traditional lining solutions.

Simon installing CCX

Irrigation Leader: How thick is CCX?

Simon Lester: CCX-M, used for canal lining, is 0.4 inches thick, with the addition of a 12-mil linear low-density polyethylene geomembrane backing. CCX-M is typically used to replace 2–4 inches of cast-in-situ concrete, shotcrete, or precast concrete elements, with or without a geomembrane underlay. The stock roll length is 164 feet long by 6.3 feet wide, equating to approximately 1,000 square feet per roll.

Irrigation Leader: Please tell us about your pilot projects in irrigation districts around the western United States.

Simon Lester: The western United States, like many places around the world, is facing acute water shortages. It is becoming critical to mitigate water seepage, which, in addition to reducing water supply and revenue, can cause waterlogging, increase the salinity of adjacent soils, or pose risks to infrastructure next to canals. We’ve just completed pilot projects for irrigation districts in California, Colorado, Nebraska, and Washington aimed at eliminating these issues. For example, in California, we completed the lining of a lateral canal that was approximately 1,500 feet long and 16 feet wide in less than 4 days. The CCX-M joints were thermally bonded to provide a low-permeability lining solution. A pond test was then conducted, and based on the measured seepage losses, the client has expressed their satisfaction with the performance of the pilot and is now considering Concrete Canvas as an alternative to their current solutions.

Irrigation Leader: What should every irrigation district know about Concrete Canvas?

Simon Lester: Concrete Canvas is a rapid, cost-effective, lower-carbon, and longer-lasting alternative to conventional liners and has variants designed specifically for the lining of irrigation canals. It allows irrigation districts to conserve water, reduce installation and maintenance costs, and self-perform. We are well positioned in the United States and globally to support irrigators and ensure successful project execution.

Irrigation Leader Magazine is available here.

Concrete Canvas Channel Lining at Greenside Mine

In 2016, Concrete Canvas was used to reline an existing channel on top of a tailings dam, preventing severe flooding and storm damage. Find out more about the project below.

Glenridding Channel Lining

The location

Glenridding Channel Lining Landscape

Greenside Mine was once the UK’s largest producer of lead ore, having been in continuous operation for over 150 years. Whilst it had been closed since 1961, there was still significant evidence of the mining techniques that were used at the site, leading to it being designated a Scheduled Monument. Having been out of use for more than 60 years, the site had also grown into a natural scree habitat, with species such as Juniper and Parsley Fern making it a Site of Special Scientific Interest (SSSI).

This was an extremely sensitive location, which required collaboration between the Lake District National Park Authority, Coal Authority, Environment Agency and the 7-5 Engineer Regiment under 4-2 Brigade to ensure the area remained protected throughout the duration of the project.

The project

As a past mining location, the site had a tailings dam which had been used to store excess material. Above the tailings dam, there was a 200m long channel, which had been causing runoff damage during periods of heavy rainfall. To protect the environment, it was decided that this channel needed to be relined with a durable solution.

Glenridding CHannel Lining Installation

Previously, the Lake District National Park Authority had used dry stone walling and poured concrete to reline the channel. However, both of these techniques posed logistical issues due to the rural location of the site and proved ineffective at preventing runoff damage. Instead, the Coal Authority, who provide geotechnical advice to the Lake District National Park Authority, recommended the use of Concrete Canvas.

The solution

Glenridding Before Glenridding After

Concrete Canvas® is the original GCCM and the first product to declare conformance to ASTM D8364-Standard Specification. This is the only internationally recognised GCCM specification standard and lists erosion control applications by three classifications, Type I, Type II and Type III. It defines the minimum performance values required for each type based on the use of test methods that are specific to GCCM materials. ASTM D8364 is an important resource for clients, consultants and contractors wishing to ensure the GCCM used on their project is fit for purpose. For Greenside Mine, we recommended that both CC8 which is Type II and CC13 which is Type III were used.

Glenridding Completed Channel Lining

The Greenside Mine site was located on a steep hillside, two miles up a remote track. This presented initial logistical issues, with no way of off-loading the materials on site. Instead, the material was by HIAB wagon to a location that was 500m away. From here, the materials were flown into position by commercial helicopter, avoiding the impact that wheeled vehicles or tracked machinery would have had on the environment.

To accommodate for the varying profiles of the channel, it was made sure that all rolls of CC8™ were batched to specific lengths. These rolls were then labelled and palletised into loads that weighed less than 950kg, allowing them to be subsequently lifted and accurately positioned by helicopter. Once the rolls were in place, they were trimmed and anchored to the ground using steel pegs and heavy rocks, with any overlaps being jointed using stainless steel screws at 20cm centres. An army-issue 10,000 litre reservoir was then used to hydrate the rolls and set them in place.

Glenridding Channel Lining Installation

The results

Glenridding Complete Channel Lining

In total, 837m² of CC8™ and 128m² of CC13™ were used to reline the channel at Greenside Mine. Since the installation, the channel has effectively prevented runoff damage to mining material. As Concrete Canvas has been approved by BBA to provide durability of 120 years, we expect the relined channel to continue protecting the surrounding environment for many years to come.

“The Concrete Canvas is still working as effectively as when it was installed. We’ve had about half a dozen really heavy rainfall events since it went in and on every occasion the runoff from the hillside above the tailings dam has been intercepted and safely conveyed directly into the beck without causing any erosion of mine material. At the end of October 2021 the site received 400mm of rainfall in six days, the wettest week since Storm Desmond in December 2015. The Concrete Canvas performed exactly as it needed to and there was no erosion of any mine material.”

Martin Lord – Project Manager, Lake District National Park Authority

Contact Concrete Canvas for Channel Lining

If you are looking for a flexible and durable concrete solution for your channel lining project, get in touch with Concrete Canvas. We can assess your project requirements to match you with the most suitable type of GCCM. With no need for plant or mixing equipment, we can even guide you through the installation process: simply unroll, secure and add water.

Get in touch

 

 

 

Concrete Canvas Channel Lining at Avoca Mines

Channel Lining Before Channel Lining After

In 2017, Concrete Canvas was used to provide scour protection to drainage channels at the Avoca Mines in Wicklow. Find out how the project went below.

The location

Copper mining is reported to have begun in the Avoca River valley in 1720 and continued, intermittently, until 1982. Consistent mineral extraction has left an environmental legacy that comprises of open pits, shafts, spoil piles and former mining buildings.

Preperation for Channel Lining at Avoca Mines

The project

During health and safety works that were being carried out by Civil and Environmental Engineering Contractor, Priority Construction Ltd., it was identified that the former mining site was impacting the quality of the water in the Avoca River. Water dischargers from abandoned copper and sulphur mines were acidic and metal laden, contaminating the nearby river water.

C Deployment for Channel Lining at Avoca Mines

It was decided that the spoil areas would need to regraded and capped, with drainage channels to redirect upstream drainage around the site, instead of through it. Whilst the original design used a combination of precast concrete channels and HDPE liner, there were concerns around the long lead in times for the precast concrete and the construction risks associated with steep slopes. Instead, Priority Construction Ltd. proposed the use of Concrete Canvas.

The solution

At Concrete Canvas, we offer Geosynthetic Cementitious Composite Mats (GCCMs), which are an alternative to traditional concrete methods. Unlike most concretes, our GCCM uses a specialist high early strength concrete, with a limited alkaline reserve. This means it has a very low wash out rate and can be directly discharged into the water course, without the need for prior treatment, making it an ideal solution for channel lining.

For this project, we recommended the use of CC13™, which is our thickest type of GCCM. However, before the installation process could begin, the channel needed to be excavated and compacted to profile. A 250mm x 250mm anchor trench was then built on either side of the channel to allow the leading edge of the GCCM to be buried, preventing any undermining. Once the channel was prepared, the CC13™ was mounted onto a spreader beam and hung from an excavator, allowing it to be easily unrolled. Each piece of CC13™ was cut to a specific profile length and dragged into place, minimising material waste.

Fixing of CC into Channel at Avoca Mines

Priority Construction Ltd. installed the CC13™ transversely to accommodate for change in the channel profile, with layers overlapping by 100m in the direction of the water flow. The overlaps were then sealed using Everbuild Clearfix adhesive sealant and screwed together using stainless steel screws. As an extra precaution against undermining, 250mm steel ground pegs were also inserted into each overlap in the anchor trenches and then backfilled with material.

Jointing of Concrete Canvas to the Channel at Avoca Mines

As the channel was located on a steep hill, concrete steps were installed to dissipate the water energy. Due to the flexibility of CC13™, it was able to be laid over each step and pinned into the vertical interface of the steps using Hilti anchors. After each day of work, the CC material was hydrated using a hose and a 6000ltr water carrier.

Hydrating Concrete Canvas for Channel Lining at Avoca Mines

The results

In total, 1,520m² of CC13™ was installed within two weeks, providing long-term scour protection and erosion control for the network of drainage channels on the site. Despite the steep and varying slopes, we achieved installation rates of over 200m² per day.

Completed Channel Lining at Avoca Mines

Following the success of this installation, Concrete Canvas is now being considered for multiple projects in the same region, in both the public and private sectors.

“After carrying out some research into alternatives for in-situ or precast concrete drainage channel we encountered Concrete Canvas. As we learned more about this solution we realised it would be ideal for the Avoca Mines Remediation Project which we had been awarded. We succeeded  in gaining approval from the client for the use of Concrete Canvas. As the project progressed it became clear that this solution provided a number of benefits when compared with traditional methods. These benefits included speed of installation and flexibility in terms of levels e.g. where there were changes in design levels. I intend to use this product on future projects where possible.

Ken Madden – Senior Contracts Manager, Priority Construction Ltd.

Contact Concrete Canvas for Channel Lining

Completed Channel Lining Project at Avoca Mines

If you are looking for a flexible and durable concrete solution for your channel lining project, get in touch with Concrete Canvas. We can assess your project requirements to match you with the most suitable type of GCCM. With no need for plant or mixing equipment, we can even guide you through the installation process: simply unroll, secure and add water.

Get in touch

 

 

The importance of weed control management

Weed control methods are vital to the survival of native plants and the safety of physical infrastructures.

As weeds compete for light, nutrients and moisture, they can grow at an accelerated rate and take over as the primary plant species. In doing so, they can eradicate native plants in a single growing season, which can be extremely harmful to the ecosystem.

When weeds grow alongside physical infrastructures, they can become a health and safety hazard. From road-sides where they can block the visibility of drivers to pipe tracks where they can cause a critical leak, weeds can quickly become a problem in peoples’ everyday lives.

There are a variety of weeds, from harmless common garden weeds to the more dangerous plants that are toxic to humans/animals or public spaces. Some can be harmful to humans from causing rashes to severe blisters when touched like the stinging nettle or poison ivy. They can also be threatening in other ways:  invasive weeds can become dangerous as they outgrow other plants killing them in the process, some can cause property damage as they grow at such a pace it becomes impossible to control and many are poisonous to animals.

The different weed control methods

There are a number of weed control methods that can be used to prevent the growth of weeds:

Organic mulch

Most commonly a form of chipped bark, organic mulch is one the most environmentally friendly methods of weed control management. When applied in a 2–3-inch layer, organic mulch helps to block the sunlight that weeds need to grow. Not only does mulch prevent weeds, it also benefits the soil by retaining moisture and releasing nutrients.

Organic mulch is a relatively short-term method of preventative weed control and will need to be reapplied at least once a year.

Geotextile Membranes

The majority of high-quality geotextiles are made from a synthetic-fibre material. When applied, geotextiles work by blocking the sunlight and preventing the growth of weeds. Whilst many fabrics are UV-protected, it is advised that they are not directly exposed to sunlight. Instead, geotextiles can be covered with a layer of mulch, providing additional weed prevention. Geotextiles will require regular monitoring to ensure it maintains its strength and quality.

Herbicides

Herbicides are a popular method of weed control for roadsides, and are currently used by local councils across the UK. Selective herbicides help to target and remove invasive species, without impacting the surrounding vegetation. These are considered the most environmentally-friendly form of herbicide, as the removal of invasive species is vital to protecting our established ecosystems.

Herbicides provide short-term weed control and need to be applied twice a year for effective weed control management.

Concrete Canvas

Concrete Canvas is a growing application for weed control management, at land development projects and limited access sites. Complying with ASTM standards, Concrete Canvas has been certified by the British Board of Agrement (BBA) for its weed suppression applications. By forming a fibre reinforced concrete layer, Concrete Canvas prevents weed growth, soil erosion and water pollution. Concrete Canvas has been tested against weed suppression and root penetration resistance according to DD CEN/TS 14416:2005, meaning weeds will not break through the material. It’s available in man-portable batched rolls, which allows for easy transportation to limited access sites and where application is required near a road or railway. Not only will CC prevent weed growth but it prevents corrosion of pipework and clear leak detection visibility.

Concrete Canvas is a long-term preventative weed control method, with a minimum design life of 50 years. Typically ten-times faster to install than conventional solutions and it allows for installation with minimal plant specialist training. One single layer of CC5 material would replace 100mm of poured concrete, saving on material and cost. With the product being a long-term solution, this would save vast amounts of money on maintenance and continuous labour costs.

Use Concrete Canvas for Weed Control Management

If you’re looking for a weed control method that is durable, flexible and environmentally-friendly, look no further than Concrete Canvas. Concrete Canvas has been used across a number of industries, including Road, Rail and Utilities for its weed control management.

To find out more about Concrete Canvas and how it can be used for weed prevention, get in touch.

Concrete Canvas are proud to announce that it has been nominated as the finalist in the 2022 South Wales Business Growth Awards for THREE categories.

  • Innovation
  • Brand
  • Environmental

The Business Growth Awards celebrate the efforts that South Wales businesses have achieved to shape the local community.

Thank you to all our staff for all your continued hard work and dedication to support our growth. Thank you to all the contractors, clients and consultants who trust us in providing the right product for hundreds of ongoing global projects, from public works to utilities and mining.

The results will be announced at the Awards Ceremony on Friday 4th March 2022.

Soil erosion in farming

Soil erosion is one of the most common concerns for farmers.

The erosion is a gradual process where water and certain weather conditions impact the soil and cause it to deteriorate. Not only does soil erosion remove the quality of the topsoil, but it also is detrimental to the land and environment, as it causes pollution in landslides and waterways. Soil erosion can also increase the risk of flooding, and in worst-case scenarios, the land could be cultivated if soil erosion is severe.

Before we look at how farmers can control erosion and minimise the impact, we’ve listed the top causes that affect the quality of the soil and farm work.

What types of erosion are in farming?

Different types of soil erosion can cause several problems. These include:

Water erosion

Water can impact the quality of soil over time. However, the amount and rate it deteriorates completely depend on how much water the soil is exposed to, and whether it’s through rainfall or flowing water. The effect water erosion has on the soil can be invisible. Farmers may see a difference in the colour of the soil over time. Farmers can control erosion by putting measures in place – both structural and cultural practises – to improve the soil infiltration to water rate.

Wind erosion

Similar to water, wind can affect the quality of the soil and cause it to erode over time. Farmers can reduce the impact that wind has on the soil by keeping it covered.

Channel erosion

In some cases where erosion is severe, a channel can form in the land if one of the banks in the land is breached.

The irreversible damage that soil erosion has is one of the reasons why farmers are always seeking sustainable solutions and soil management systems to control erosion and protect their agricultural land.

What is erosion control?

Erosion control is the practice of preventing water from eroding the landscape. There are different erosion control methods that farmers can use to stop their land and soil from eroding.

How can farmers control erosion?

Planting vegetation

One way that farmers can control erosion in the soil is by planting vegetation. This method involves planting crops that are suitable for erosion control. These are deep-rooted plants, such as trees or woodland, which diverts surface water into channels.

Contour farming

Another way that farmers can control erosion and manage surface water is physical earthworks to create water channels to divert surface water away from agricultural land. Not only is this method costly, but it’s also timely and disruptive to the environment and biodiversity.

Cover the area with geosynthetic material

Covering the area with geosynthetic materialsheeting is a popular method that farmers use to control erosion. One product that can control erosion and cause minimal damage to the ground is Concrete Canvas. Concrete Canvas is the original Geosynthetic Cementitious Composite Mat (GCCM).

Concrete Canvas is a three-dimensional fibre matrix that contains a specially formulated dry cementitious mix. The PVC backing ensures that Concrete Canvas is completely waterproof while the reinforcement of cementitious mix prevents cracking. As a result, Concrete Canvas is a thin, durable waterproof and lower-carbon alternative to traditional concrete.

Concrete Canvas is one of the most effective ways that farmers from around the world can use to control erosion as it covers the entire soil surface. Using Concrete Canvas to control erosion means there is less concrete in the ground and it can divert surface water efficiently.

Channel Lining Before Channel Lining After

The benefits of using Concrete Canvas

Concrete Canvas has many benefits as an erosion control application, including:

Easy and quick installation

Concrete Canvas is used in the agriculture and farming industries because of its easy and fast installation. The material is laid at a rate that’s ten times faster than conventional solutions that are used to control erosion in farming.

Concrete Canvas is also easy to install and doesn’t require on-site mixing or measuring. Available in batched rolls, Concrete Canvas can be unrolled on the surface fixed into place and hydrated.

Minimal disruption

As Concrete Canvas doesn’t require a large team or equipment to install, the erosion control application is less intrusive to inaccessible and environmentally-sensitive areas.

Cost-effective

The speed and ease of installing Concrete Canvas mean that farmers can cut the costs of time and labour it takes to apply an erosion control measure and preserve the quality of their soil.

Sustainable Alternative

Concrete Canvas is a low mass, lower carbon technology, which uses up to 95% less material than conventional solutions, making it a lower carbon alternative to conventional erosion control methods that farmers can use.

Less specialist equipment and heavy plant

Using Concrete Canvas as an erosion control application requires less specialist equipment and heavy plant, which means less damage to the agricultural land.

 Learn more about Concrete Canvas

For more insight on how farmers can control erosion, specifically by using Concrete Canvas, you can contact our team for more information.

Enquire now

Contact Us